Topaz Bridge Expansion & Replacement | McCammon, Idaho
Idaho’s heavily used trucking route and bridge (circa 1940) expands from 2 to 4 lanes to increase safety and capacity using InsulFoam Geofoam.
Download the Case Study PDFIdaho Transportation Department’s first EPS Geofoam project was designed by Terracon Engineers and JUB Engineers of Boise. EPS was specified as a soil replacing embankment fill material due to poor foundation soils and 2 steel fish culverts that could not bear the weight of traditional soil fill. A new three-span, bridge replaced the existing bridge (from the 1940’s) crossing rail road tracks and expanding the highway to 4 instead of 2 lanes. 23,000 cubic yards of large block EPS was installed by Scarsella Brother Inc. and supplied by Insulfoam.
THE PROBLEM
The expansion of the US-30 and bridge replacement required a new fill embankment to support the new roadway and bridge approach on a very steep side slope.
The new (600 ft long) expanded bridge clears The Pontneuf River as well as the Union Pacific Railroad tracks, and required a new higher grade of both the bridge structure and the existing roadway to support the new wide and long center spans.
As a result the new bridge approach embankment would be 45-50 feet high, too costly to be retained by conventional concrete cantilever or MSE wall, and raised concerns about global stability.
Further challenges to the project design were the site conditions. Located adjacent to the Portneuf River, shallow bedrock and loose or soft sediments underlie the new approach embankment. This both challenged the new roadway embankment’s strength and stability, and limited deep foundation designs required with concrete walls.
THE EPS GEOFOAM FILL SOLUTION
To reach the new bridge’s approach embankment height of 45 feet, engineers chose a combined fill solution. The lowest 15 feet was a small earthen embankment, while InsulFoam GF constituted the upper 30 feet. 4 1/2 feet of granular fill retained in wire gab ions and an asphalt pavement section were installed directly on top of the EPS blocks to complete the full height of the new embankment.
The soft sediments underlying the site required the lower earthen embankment to settle (80 days), but the InsulFoam GF block fill required no additional surcharge time or secondary compaction by the contractor. Traffic moved on the existing roadway throughout the installation of the upper embankment, which was a key factor for the expansion to finish when weather conditions permitted.
The ultra lightweight nature of EPS allowed the total design weight of the tall embankment to be week under the bearing capacity of the poor foundation soils which aided ITD in successfully completing their first EPS Geofoam project.
Geofoam Lightweight Geo-synthetic Fill:
- Soft Soil Remediation
- Lateral Load Reduction
- Slope Stabilization
- Buried Utility Protection
- Structural Void Fill
- Predictable Elastic Modulus
- Exceptional Strength & Stability
- Exceeds 75 year Design Life
- Weather, Insect & Mold Resistant
- 100% Recyclable
MORE GEOFOAM SOLUTIONS IN HIGHWAY CONSTRUCTION
- Lightweight Geofoam Fill Supports Highway Construction, Siteprep Online
- Geofoam Saves Time, Money During Three Projects, Better Roads Magazine
- Geofoam Offers Performance and Efficiency for Bridge Reconstruction, Modern Contractor Magazine